Barclays Innovation Centre — Knutsford, UK

HV Cable Termination Repair at Barclays Innovation Centre, Knutsford

Northern HV was appointed to carry out essential high voltage cable repairs at the Barclays Innovation Centre in Knutsford following the need to replace a damaged section of cable between the Ring Main Unit (RMU) and transformer.

Client

Barclays Innovation Centre

Location

Knutsford, UK

Contractor

Northern HV Ltd

Project Overview

Northern HV was appointed to carry out essential high voltage cable repairs at the Barclays Innovation Centre in Knutsford following the need to replace a damaged section of cable between the Ring Main Unit (RMU) and transformer.

During the project, our engineers also identified a second cable that required remedial work due to an issue with the original installation. Both repairs were completed as part of the works, ensuring the integrity of the high voltage network before it was returned to service.

Our engineers completed the replacement of the affected HV cable, installed new HV cable terminations where required and carried out comprehensive testing to ensure the installation was safe and ready for service.

Scope of Works

The project involved:

  • Removal of the existing high voltage cable between the RMU and transformer.
  • Installation of a new HV cable.
  • Repair of a second HV cable where the original installation was found to be incorrect.
  • Installation of new HV cable terminations at the RMU and transformer.
  • VLF (Very Low Frequency) testing to verify the integrity of the completed cable installations.
  • Confirmation that the circuits were suitable for energisation.

Delivering a Safe and Reliable Installation

Correctly installed and tested cable terminations are essential to the long-term reliability of any high voltage network. Our experienced engineers completed both the planned cable replacement and the additional remedial repair before undertaking comprehensive VLF testing to verify the integrity of the installations.

By identifying and rectifying the incorrectly installed cable during the project, Northern HV helped ensure the network met the required standards before being safely prepared for energisation.

Project Outcome

The project was completed efficiently, with the defective cable replaced, the incorrectly installed cable repaired and new HV terminations installed where required. Comprehensive VLF testing confirmed the integrity of the completed works, allowing the high voltage system to be safely prepared for energisation.

Frequently Asked Questions

Need HV Cable Repairs or Commissioning?

Whether you require HV cable replacements, cable terminations, electrical commissioning, testing or planned maintenance, Northern HV delivers safe, professional solutions for commercial and industrial electrical infrastructure throughout the UK.

Related Case Studies

Confidential Utility Client

UK Grid Substation

400/33kV 60MVA Transformer Installation & Commissioning

Northern HV delivered full installation and commissioning of a 400/33kV 60MVA power transformer at a UK grid substation. Vacuum oil filling, IEC 61850 protection integration, and energisation on schedule — over 8,000 man-hours without incident.

Learn more

Confidential UK DNO / ICP

UK Grid Substation

145kV Eco-Efficient Circuit Breaker Installation & Commissioning

Northern HV installed and commissioned a Hitachi Energy LTA 145D1 145kV circuit breaker using eco-efficient COâ‚‚ gas technology. Full mechanical, electrical, and gas handling works delivered within a constrained outage window.

Learn more